Project Scope

We delivered a comprehensive backup solution with 2 robust 500kVA containerised generators. To guarantee smooth operation, we installed a secure, double-skinned and fully welded fuel balancing system featuring leak detection monitoring for complete environmental protection. An integrated filling cabinet with a high-level alarm unit ensures safe and automated refuelling. Finally, we meticulously installed all the necessary generator control cables for seamless operation.

Project Overview

Installation of 2 x containerised 500kVA generators, a double skinned fully welded fuel balancing system with leak detection monitoring and 1 x fill cabinet with high level alarm unit.

We also installed all associated generator control cables.