Project Scope
Generator Fan Alignment
Coupling
Fuel System - Tanks/Polishing/Piping/Control
Plant Movement, Offload and Positioning
Install of Fuel and Inert Gas Systems
Bespoke Exhust Terminals - Venturi
Cooling & Combustion Air Systems
Integration into BMS
LV Install - Switch Gear
Cable Install & Containment
Bespoke Control System
Structural Steel - Design, Build, and Erect
Test & Commissioning
Project Overview
ASEE Group was awarded the Generator Integration installation package for a 30,000 m² data centre in Belgium.
A world-first for this project, the 60MW energy-efficient data centre operates entirely without refrigeration. Instead, it uses chilled water from a nearby industrial canal to cool the servers, alongside a solar farm that contributes to on-site power generation. This data centre campus is leading the way in climate-friendly data solutions.
Sector
Data Centre