We have started work here on our installation package, this will see us carry out the installation of 10no. 2.5MVA/1.8MW CTM sets, we will also install the fuel pipework here including the day tanks for these sets.
Our installation of the bulk fuel tanks has been completed and work will begin very soon on the building of the inlet and outlet attenuation.
Below are some pictures of the bulk tanks installation.
.
.
.
.
Below are some pictures of our vertical duct installation.
.
.
.
.
.
.
Our works here are now complete and we are just assisting with commissioning at the minute, |