  • Major Data Centre - North Dublin Update

    8 May 2008

    Work is progressing on site very quickly, with generators being delivered last week and alot of the fuel lines installed. Below are some recent pictures of off-loads etc.
    Read More

  • Phase 2 of Works At Slough Data Centre

    15 April 2008

    Following on from our phase 1 works in 2007, we returned to site to carry out phase 2 of the works which is the installation of new fuel pipework too enable connection to three new daytanks.
    Read More

  • Our work commences on major Data Centre in North Dublin

    15 March 2008

    Work carried out on behalf of Cummins UK. Our work commences on major Data Centre in North Dublin. Work has been ongoing for the last 4 weeks and is expected to carry on until June 2008. Our range of works here will incorporate installation of fuel lines, setting in place off 4 no. 2.5KVA MV gensets and also installing output cables and control cables for these sets.
    Read More

  • CTM Site Visit

    12 March 2008

    ASEE team, Factory Visit- Milan, Italy. First 5 of 10 MTU MV gensets for new European data centre.
    Read More

  • CTM Site Visit

    12 March 2008

    ASEE Team, Factory Visit - Milan, Italy. Here we can see a collection of MV sets ready for delivery to UK.
    Read More

  • Multi Occupancy Data Centre fit out completed in South London

    1 March 2008

    Installation on behalf of Mercury Engineering Ltd First 3 of 31 generator sets being offloaded at a multi-tenancy Data Centre in South London - Typical ASEE Ltd offload procedure Gen. set container final assembly Fuel lines -gravity fed twin wall Typical 'A' supply switchroom - and the dupllicate 'B' switchroon Colour Identified Final electrical connections to multiple 3MVA generator sets - 8 x 400mm 4 core swa/LSF from output link box Multiple HV switchboard sections HV sw
    Read More

  • ASEE Direct Labour

    1 February 2008

    Typical Data Hall Build. ASEE Ltd personnel arranging switchroom fit out. General Hall area equipment positioning by ASEE Ltd.
    Read More

  • Major Data Centre in Outer West London

    7 November 2007

    This project saw the fuel installation for 13no. 11KV generator sets. Completed by ASEE Ltd November 2007.
    Read More

  • Three Container Sets for North England Data Centre

    2 April 2007

    ASEE Ltd offload and positioning of first of three Containerised sets at a North of England Data Centre. Set in position and roof mounted systems being added. Generators are designed to facilitate the use of 4000 amp resin bus bar rather than several single core armoured cables for generator output. All three sets now in position and ASEE Ltd installation and precomissioning checks underway. Generators are 2.5 MVA, by CTM Italy. Installation completed by ASEE Ltd in March 2007.
    Read More

  • Data Centre at Sunderland

    27 January 2007

    Completion of exhaust discharge flues after installation of three plant room P2000 Generators at a new data centre near Sunderland, completed by ASEE Ltd January 2007. Generators by CTM Italy.
    Read More

  • Generators for Slough Data Centre

    27 January 2007

    Installation of 2 x P1500 Container sets, including fuel storage, completed by ASEE Ltd in Jan 2007 at a new Data Centre near Slough UK. TWIN WALL FUEL LINE FABRICATION
    Read More

  • Additional Generators Installed at Canary Wharf

    27 January 2007

    Two additional 2.5MVA Medium Voltage generators for major banking corporation at Canary Wharf. Installation includes external roof Radiators and new air ventilation, external discharge exhaust flues, MV output and control cabling giving a total of five 2.5MVA Medium Voltage sets within one basement plantroom. Generators by FG Wilson Engineering Ltd. Installation completed by ASEE Ltd January 2007. Generator Offloading Electrical Installation
    Read More

  • Generator Installation at Isle of Man

    20 January 2007

    P1250 Generator system being installed for Douglas, Isle of Man water treatment works, completed by ASEE Ltd mid January 2007. Fuel Oil storage tank being hoisted to final position at Douglas.
    Read More

  • Six Container Sets - Outer London

    1 February 2006

    High level view of major project - six containerised 11kV generator sets presently being installed outside London. One of the two bulk fuel silo storage tanks being lowered into position.
    Read More

  • London Riverside Site

    20 January 2006

    New in-basement 100,000L tank, fabricated on site by ASEE Ltd. Tank is 1m height and building subject to weight restraints due to soft ground as the location is in close proximity to river Thames. Fuel system is feeding three P1500 Generators recently installed at Level 12 in this building by Aidan Strain Electrical Engineering.
    Read More